Project Success Story – Tension between Business and IT

Project Success StoryThis is the story about a project manager, Gren Gale, who was working for a large insurance company in the UK who wanted to update their CRM system to provide a much smoother experience for call centre operators and allow better integration of customer information between call centre and back office.

Politics

While the business area was very anxious to get on with the change, there was friction between business change and IT over the choice of system and the degree of involvement of IT in the implementation.  This particular area of business change had suffered from previous poor experience with the IT department and wanted to bypass them.  With IT having strict rules for the compliance of any new system to its technology standards, there were political issues to handle as well as a complex implementation to manage.

Outsource

Tension between IT and BusinessA tender was issued by IT to six vendors, using requirements put together by business change.  As seemed almost inevitable in the situation, business change preferred the system that was the least compliant with IT standards, while IT preferred another system.

Negotiations between the IT project manager and IT’s preferred vendor resulted in a big reduction in up-front costs by the vendor who were keen to get a foothold in the Insurance sector.  Despite luke-warm support from business change, the recommendation to go with this vendor was presented to the director of the business area and approved.

This left IT satisfied, but business change feeling not entirely happy about the choice.

Analysis and Design

Meetings were arranged to agree a final design between the business area and the vendor.

These went well, but hit a couple of issues:

Project Success Story: National Point of Sales System Upgrade

By Linky van der Merwe

Success Story SharedThis project story from project manager, Anwar Rawoot, is about the migration from a legacy Point of Sales (POS) system to a new POS system at 265 retail stores nationally that took three years to complete.

The complexity was in the fact that the project team only had a 12-hour window from the time a store closed until the next morning it opened to do the replacement, which included network infrastructure, shop fitting, POS and testing. A shop’s data would be migrated overnight and once the new system is in, it was migrated back to the new system.

Challenges

The project’s biggest constraints were that when server problems were experienced, it would take 8 hours to rebuild and in the case of till problems, it would take 3 hours to rebuild.

The way it was executed, was to do one store each night. All work had to be done after hours and there was only one team per region to do the work. They had to sleep during the day and work at night which had a family impact.

Working after hours

The challenge was how to work a 5-day week back-to-back and then an additional 24 hours shift. People became overworked, and the quality of work dropped. Some people even became ill over time. It also took three months to train people to the right level of expertise.

Eventually the plans were changed….. Read on

***************************************************************************

Part of the Success Stories Shared initiative to collect Success Stories from experienced project/programme managers in order to share experiences and to promote learning across the project and programme management community. If you would like to share your project story and make a contribution to the bigger project management profession, contact me on linky@virtualprojectconsulting.com

Success Stories Shared
Success Stories Shared